Template by Industry / Domain
Manufacturing charters carry weight other charters do not: a wrongly scoped line upgrade can stop production for weeks, breach OSHA process safety requirements, or miss the shutdown window the supply chain planned for. The six sections below are specific to plant capex.
Three factors set manufacturing project charters apart from generic capex charters. First, the asset under change is a production line that must come back online with measured OEE, not just "a system that works". Second, the project must fit a planned downtime window negotiated with Supply Chain; missing the window pushes overrun costs to six figures per day. Third, the project must pass formal EHS and regulatory gates (PHA revision, Pre-Startup Safety Review, OSHA machine guarding review) before the line can restart.
The reference sources for manufacturing charter standards are the Society for Maintenance and Reliability Professionals (SMRP) best practices, OSHA Process Safety Management (29 CFR 1910.119) for covered processes, and the equipment vendor's commissioning protocol.
1. Production Asset Scope
Which line, cell, machine, or SKUs are in scope. Bounded by plant, line number, and (where relevant) shift pattern. The most common reason a manufacturing project blows out is a vague 'modernise the plant' scope.
2. OEE Baseline and Target
Current Overall Equipment Effectiveness (Availability x Performance x Quality) and the post-project target. Measured in the production system, not estimated.
3. Planned Downtime Window
When the line can be offline, for how long, with what compensating production from sister lines. Approved by Operations and Supply Chain together.
4. Changeover and Run-Rate Targets
Time to changeover between SKUs, and steady-state run rate post-implementation. Often the deliverables that justify the capex.
5. EHS and Regulatory Scope
Permits required, Process Hazard Analysis (PHA) updates, MSDS revisions, and named EHS approver. Skipping this is the most common cause of project delays at commissioning.
6. Spares and Operator Training
Recommended spare parts inventory at go-live, operator training plan and certification before line release back to production.
Worked example for a USD 4.6M packaging-line upgrade with a 3-week planned shutdown. Numbers are typical for mid-volume consumer packaged goods upgrades; OEE benchmarks reflect SMRP and OEE.com published industry standards.
Project name
Brookline Plant Packaging Line 7 Upgrade
Duration
9 months (1 Jun 2026 to 28 Feb 2027), with primary shutdown window 2-23 January 2027 (3 weeks)
Budget envelope
USD 4.6M total (USD 3.8M equipment + USD 480K installation + USD 180K commissioning + USD 140K training, plus 8% contingency reserve)
Line: Packaging Line 7, Brookline Plant, Massachusetts
SKUs: All 18 active SKUs currently run on Line 7 (consumer pack sizes 250 g, 500 g, 1 kg).
Shifts: Currently 2 shifts (06:00-22:00, Mon-Sat). Post-upgrade target: 3 shifts (24-hour Mon-Sat).
Excluded: Lines 5 and 6 (separate cohort 2028). Bulk packaging (handled by Line 9). Repackaging cell (not in scope).
| Component | Current | Target |
|---|---|---|
| Availability | 78.4% (32 shift-hours per week of unplanned downtime) | 91.5% (under 12 shift-hours/week unplanned) |
| Performance | 82.1% (target speed 220 packs/min, actual 181 packs/min) | 94.0% (sustained 207 packs/min against target 220) |
| Quality | 96.8% (giveaway and rejects) | 98.5% |
| OEE | 62.3% | 84.7% |
World-class OEE benchmark is 85% (SMRP and OEE.com). The target of 84.7% sits at the boundary of world-class.
Primary shutdown: 2-23 January 2027 (3 weeks, lowest annual production demand period per 5-year demand data). Sister Lines 5 and 6 will absorb 70% of the SKU volume during shutdown (verified by Supply Chain capacity model, October 2026). Remaining 30% covered by 4 weeks of safety stock built up between October-December 2026.
Current: Average SKU changeover: 47 minutes (cleaning + format change + first-pack verification).
Target: Average SKU changeover: 22 minutes (SMED methodology applied; quick-change formats engineered into new line).
Benefit: At 18 changeovers per week, the saving is 7.5 hours/week of production time, equivalent to 11% additional capacity.
Related on this site
Updated 2 May 2026